22 October 2009 3:43pm |
Site Administrator
After nearly a of month of excavation work, the bulk of it is almost finished. The floor level of the new building will match the existing building and so the ground level has had to be reduced. This has been completed and work continues on digging the foundations. There is also a lot of behind the scenes work completing the detailed design work for the fixtures and fittings.
Over the next month we should see:
- the foundations completed
- the start of some of the wall structures being built
- and hopefully the huge steel frame for the hall begin to go up.